Architect: VSWC Architects
Contractor: Adena Corporation
Sub-Consultant: Farnham Equipment Company
Completion: August 2018
January 2018 led to numerous capital improvements for Ashland City Schools including renovation of the Community Stadium Home Side Grandstand. The project included an elevated front deck, an accessible ramp, aisle rails and new rear guardrail fencing as well as powder-coated guardrails in lieu of chain link fencing for better patron sight lines.
With the main goals of ADA accessibility and safety, the district was able to add 28 elevated handicap-accessible seating areas along with companion seating in the front row with ramp mobility for others to pass behind. Aisle-ways were widened, and an additional aisle-way was added, to add handrails and intermediate aisle steps to provide added safety and ease of access for patrons.